  • 11,000 LF of 16'' transmission line on Haeckerville Rd. 
  • 16,000 LF of 24'' water transmission line along Weil Rd. 
  • 2,044 LF of 16'' waterline at Bolton Rd. Meter Station
  • Phase 2 Waterline Construction Hallies Ranch
  • Relocation of 20'' ductile iron waterline
  • TxDOT FM 1103 Expansion