FM 725 Waterline Relocation Project

Project Background

This project is to relocate the waterline in conjunction with TxDOT’s widening of FM 725 from County Line Road to Schumans Beach Road.

Project Status

The engineer coordinates with TxDOT and is preparing the preliminary design for review by GVSUD and TxDOT. Upcoming work includes additional surveying, coordination meetings with TxDOT, and a draft agreement.

Construction Cost Estimate: $1,206,000.00

Awarded Contract: Not awarded at this time