FM 1103 Water Relocation Phase I

FM 1103 Water Relocation Project showing water lines in the ground
FM 1103 Water Relocation Project Showing Road Bore.

Project Background

This project is in response to the upcoming widening of FM 1103. Green Valley Special Utility District staff are working with TxDOT to identify conflicting lines and relocate as necessary. TxDOT funds the relocation of eligible waterlines due to the roadway's construction, but any upsizing of lines is the responsibility of GVSUD.

Project Status

Phase I – The project is complete and will be presented to the Board for closeout in April.

Phase II – Notice of award was given on March 19th, and pre-construction meeting is scheduled for April 21st. 

Phase I Construction Cost Estimate: $1,145,124.00

Phase I Awarded Contract: $1,145,124.00

Phase II Construction Cost Estimate: $1,072,000.00

Phase II Awarded Contract: $1,109,297.00