FM 1103 Water Relocation Phase I

Excavation of the Receiving Pit for the Coy Lane Bore
Construction of the Steel Casing Assembly for the Coy Lane Bore

Project Background

This project is in response to the upcoming widening of FM 1103. Green Valley Special Utility District staff are working with TxDOT to identify conflicting lines and relocate as necessary. TxDOT funds the relocation of eligible waterlines due to the roadway's construction, but any upsizing of lines is the responsibility of GVSUD.

Project Status

Phase I –Part 1 is completed and closed out. GVSUD is waiting on reimbursement from TxDOT.

Phase II – The Contractor has mobilized, and materials have been delivered to the site.  They are preparing for the bore across Coy Lane and the installation of water line between Coy Lane and Sutherlun Lane. 

Phase I Construction Cost Estimate: $1,145,124.00

Phase I Awarded Contract: $1,145,124.00

Phase II Construction Cost Estimate: $1,072,000.00

Phase II Awarded Contract: $1,109,297.00