Welding of the Roof Access Tube
Completion of the Third Shell Layer of the Steel Bowl

Project Background

These projects include two elevated storage tanks to replace Plant 3 and the previous Plant 4 (Plant 12).

Project Status

The contractor began the ground phase painting of the tank bowl on April 15th. The tank is expected to be raised at the end of June.

Construction Cost Estimate: $ 2,452,067.75

Awarded Contract: $3,3374,000.00