Project Background

The Weil Road Booster Pump Station Fill Line Project involves providing a transmission line from the CRWA Wagner Booster Station to the Weil Road booster pump station to add additional capacity to the Plant 1 elevated storage tank. Funding for this project is anticipated through the USDA Rural Development program.

Project Status

The final walkthrough was completed on December 10, 2020. The project will be presented to the Board for final approval and release of retainage upon additional vegetation growth.

Construction Cost Estimate: $4,058,337.80

Awarded Contract: $3,797,210.01