South Haeckerville Road Water Transmission Line

Installation of 16'' x 4'' Tee Connection
Restoration of Pavement for Open Cut Crossing Installation

Project Background

The intent of the project is to provide fire flows to developments near Trainer Hale Road and Interstate 10. The Cibolo Creek Municipal Authority is preparing for construction of a wastewater treatment plant and an adjacent development is in the beginning phases of design for a truck stop and motel.

Project Status

The Contractor completed all roadway bores including the open cut of Lower Seguin Road, and continues to work on the waterline. The Contractor is on schedule to complete work within the contract time.

Construction Cost Estimate: $1,568,800.00

Awarded Contract: $1,199,126.54